Tange-e-Bijar and Kaman kuh Gas Field Development Project
TarhoPalayesh
Project Brief Description
Project Title | : |
Tange-e-Bijar and Kaman kuh Gas Field Development Project |
Client | : |
Iranian Central Oil Field Company |
Consultant |
: |
Tarh-O-Palayesh Engineering Company |
Type of Contract |
: |
Basic Design and preparation of EPC Tender Documents |
Duration of Project |
: |
From 2000 to 2001 |
Cost Estimation |
: |
57,000,000 USD |
Engineering Man Hour |
: |
47,000 |
Project Brief Description
|
:
|
In order to produce and process of 175 MMSCFD gas and 4,000 BPD condensate from Tange-e-Bijar and Kaman koh gas reservoir, Iranian Central Oil Fields Company has defied the above mentioned project. This project includes 3 wellheads and central facilities, gathering and transmission pipelines |
Related projects
- « Previous
- 1
- 2