NISOC Gas Pipelines
Project Brief Description
Project Title |
: |
NISOC Gas Pipelines |
Client |
: |
National Iranian South Oilfields Company (NISOC) |
Consultant |
: |
Tarh o Palayesh Engineering Company |
Type of Contract |
: |
Detail Design and Preparation of PC Tender Documents |
Duration of Project |
: |
From 2015 to 2018 |
Cost Estimation |
: |
IRR 7,202,770,000,000 equivalent €148,000,000 |
Engineering Man Hour |
: |
109,250 |
Project Brief Description
|
:
|
In order to maintain production continuity & safe operation, NISOC, by defining this project intends to develop parts of pipelines & relevant facilities including 1) Five 16″ pipelines with total length of 26Km from Marun gas injection unit to a new 16″ header with a length of 29Km in order to inject gas in 16 wellheads of Marun oilfield through 6″ branches with total length of 13 Km including 8 pig launching/receiving stations and 2) Three 20″ pipelines with a total length of 55Km and a 24″ pipeline with a length of 32.5Km collecting associated gas from Marun production units to feed NGL plants including 8 pig launching/receiving stations and 3) Aghajari gas lifting ring, 6&8″ in size and 122Km in length plus, 4″ branches to 107 wellheads of Aghajari oilfields with total length of 103Km including wellhead facilities upgrading and 5 pig launching/receiving stations and 4) One 20″ pipeline with a length of 7.7Km that starts from Karanj sludge catcher unit No. 300/500 to inject gas in 6 wellheads of Karanj oilfield. Detail engineering services as well as PC tender documents preparation has been performed by TOP Engineering Co. |
Project scope of work
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The main volumes of project implementation
Earth work
Concrete Buildings & Shelters Fenced / Bounded area Steel structure Pipeline installation Piping installation Cable laying Equipment installation
|
23,300,000
30,000 200 35,000 530 390 430,000 50 110
|
m3
m3 m2 m2 Ton Km Inch-Dia Km Ton
|