TOTAL SOUTH PARS – OPERATOR TRAINING SIMULATOR (OTS)

TarhoPalayesh

Project Brief Description

Project Title                     

:

TOTAL SOUTH PARS – OPERATOR TRAINING SIMULATOR (OTS)

Client

:

RSI

Consultant 

:

Tarh o Palayesh Engineering Company

Type of Contract             

:

Engineering

Duration of Project

:

from 2000 to 2001

Cost Estimation

:

——–

Engineering Man Hour

:

10,000

Project Brief Description

 

 

 

 

:

 

 

 

 

 

The French company RSI, intend to prepare Operator Training Simulator (OTS) for Total South Pars (TSP) phases 2 and 3 by INDISS software

The goals of this simulator are :

1) Use as an instructional instrument in the training of operators on the proper procedures for plant operation. This includes normal operation and start-up and  shutdown.

 2) Training of the operators in equipment malfunctions, emergency procedures and the handling of alarms.

Preparation of Operator Training Simulator (OTS) has been performed by TOP engineering Co.

Project scope of work

The simulator will be a dynamic model of the following installations:

  • Production Wellhead Platforms 1 and 2 and 32 “ Pipelines
  • Reception facilities of phases 2 and 3 (units 100, 103, 200 and 203)
  • MEG regeneration (unit 102) and 4 “ MEG back lines
  • Gas Treatment
  • Utilities

The main volumes of project implementation

Project Image Gallery

Related projects

4-8

South Gashu Gas Field Development Project

7-3

Razi Petrochemical Sulphur Forming Plant Project

2-5

Esfahan DMT Factory Waste Water Treatment Unit Project

1-14

Ahwaz Steel Complex Direct Reduction Plant